weichen 53d1be5349 feat(quote,squad): B5 input validation + review invariants; A5 non-critical step degradation
P10 backlog triage (implement B5+A5; A6 already fixed in-tree, D5 keep shared
KB, R1 separate task, R4/R5/R6/R7 no-go with evidence):

- quote: ValidateInput (empty names/hours, negative/NaN/Inf fail-closed);
  reviewSummary invariants (line sums = total; buffer 20%/margin 40%/tax 7%
  rate self-consistency) enforced before Excel write
- squad: StepSpec.Critical *bool (nil=critical default); non-critical step
  failure marks step degraded + gov audit, workflow continues, final status
  degraded with DegradedSteps list; critical failure semantics unchanged
- tests: 5 new cases (quote 3 + squad 2), full short suite green, arch-check pass
2026-09-25 17:10:35 +00:00

2.7 KiB
Raw Blame History

P10 backlog 价值评估与择优实施 测试报告

一、 测试背景 (Background)

总控 P10:两份 backlog(p6-backlog + rdev-phase2)逐项评估定做/不做。评估结论:B5(报价校验复核)与 A5(小队非关键降级)本批实施;A6/D5/R1/R4–R7 登记不做(依据见 任务文)。

二、 测试目标 (Test Objectives)

  1. B5:quote 输入校验 fail-closed(空名/空表/负值/NaN/Inf);复核不变式(行合计=总额、buffer/margin/tax 费率自洽)。
  2. A5:非关键步骤失败转 degraded 继续;关键步骤失败行为不变。

三、 测试方案与环境 (Test Plan & Environment)

  • OS:Linux;Go 1.27.1;worktree .worktrees/backlog-triage-p10-2026-09-25(base dev 4bdbb0da)。
  • 层级:工程层单测(真实 WorkspaceEngine/PrepareWorkspace + fail-first backend)。

四、 预期结果 (Expected Results)

# 用例 预期
T1 TestValidateInput(7 组畸形输入) 全部拒绝;合法输入通过
T2 TestCalculateAndFillRejectsBadInput NaN hours 返回 error、无文件产出
T3 TestReviewSummaryRateInvariants 自洽数据通过;buffer 失衡被拒
T4 TestNonCriticalStepDegradesAndContinues Success=true + DegradedSteps=[step_01] + wf=degraded + step_02 completed
T5 TestCriticalStepFailureStillAborts err 非 nil + wf=failed + 后续步骤不跑

五、 实际测试结果与判定 (Actual Results & Evaluation)

  • T1:PASS(7/7 畸形拒绝 + 合法通过)
  • T2:PASS
  • T3:PASS(初版测试数据 TotalPrice 与行合计不一致被正确拦截——复核器按预期工作;修正测试夹具后通过)
  • T4:PASS(backend.calls=2 证明降级后续跑;step_degraded 治理审计落 gov_audit)
  • T5:PASS(backend.calls=1,默认关键语义零变更)
  • 全量:go test -short ./... 无 FAIL;arch-check --mode block production gate passed

六、 自动化测试套件汇总 (Test Suite Execution)

套件 结果
go test ./internal/quote/ PASS(4 用例含既有 TestCDOQuoteGeneration)
go test ./internal/squad/ PASS(含 2 新用例 + 既有全量)
go test -short ./...(全仓) PASS(0 FAIL)
arch-check --mode block PASS

七、 测试结论与后续优化建议 (Conclusion & Next Steps)

  • B5/A5 达到交付终点;A6(已修复)、D5(维持共享)、R1(另立任务)、R4/R5/R6/R7(前置未满足/已落地/低优)评估结论入档。
  • 后续:R1 N/A 生成模式若启动需跨 manifest/bizdev/squad/前端四点联动独立认领;squad 并行组降级(本批只覆盖串行路径)可作 A5 二期。